CitiPower Development Ltd Sensitizes Public on Alaoji–Onitsha Transmission Line Project, Begins Compensation Disbursement… funds on our cheques unfair—beneficiaries

By Dan Opara
CitiPower Development Limited has issued important information to residents and stakeholders regarding the ongoing rehabilitation and expansion of the 330kV transmission line from Alaoji to Onitsha, covering approximately 138 kilometers.
The project, which involves upgrading from Single Circuit (SC) to Double Circuit (DC) Quad Core Conductor, is being implemented in line with national electricity transmission standards under the Transmission Company of Nigeria (TCN).
In a significant development, the company and its management team have commenced the disbursement of financial compensation to affected persons.
Some beneficiaries from Imo State and Abia State received their compensation payments in cheques today, Thursday, April 2, 2026, during an event held at Rockview Hotel, Owerri.
The exercise marks a major step in the implementation of the Resettlement Action Plan (RAP), aimed at ensuring that all impacted individuals are duly compensated and supported.
However, reactions from some beneficiaries have been mixed, as a number of affected individuals expressed dissatisfaction with the compensation amounts.
Some individuals who spoke to ThePressman Newspaper and other media practitioners shortly after receiving their cheques lamented that the payments did not reflect the true value of their properties.
According to some affected persons residing in the Ama Wire axis of Orji and Egbu areas of Owerri, it is unfair to compensate a property owner with ₦2 million for buildings valued at about ₦10 million.
One of the beneficiaries, Elder James Madu, a 98-year-old shoemaker from Ezinihitte Mbaise Local Government Area of Imo State, who currently resides in the Ama Wire area of Orji, narrated his ordeal.
He disclosed that his property, comprising four rooms and lock-up shops valued between ₦9 million and ₦10 million, was compensated with a cheque of ₦2 million.
The elderly man frowned at the development, describing the compensation as grossly inadequate and unacceptable, while appealing to both the State and Federal Governments to intervene by increasing the amount to enable him secure a new place of residence.
According to the company, compensation has been provided to affected individuals as part of the RAP to help restore livelihoods and replace affected assets, including crops, buildings, and other properties located along the transmission corridor.
Beneficiaries have been advised to utilize the funds judiciously, with additional support services available to guide them on effective financial management and investment.
For inquiries and assistance, affected persons can contact: 08037135876.
CitiPower emphasized that all affected structures must be removed within three months after receipt of compensation.
The company warned that failure to comply within the stipulated timeframe may result in enforcement actions, as the transmission corridor must remain free of encumbrances for safety and operational efficiency.
Affected persons who may have complaints or concerns are encouraged to follow the established grievance procedures.
To ensure proper handling of complaints, individuals are required to:
Submit complaints through the designated channels, provide valid identification, engage recognized representatives where necessary.
Residents can reach the project offices through the following locations:
Imo State, at Uratta Timber Market, Aba – 08033193034, and No.129, Ndubuisi Kanu Avenue, Owerri – 08024337604.
In Anambra State, No.
608, Old Market Road, Onitsha – 08021480035.
Additional information is available online at: https://pgmnigeria.com/rap
info@pgmnigeria.com
The company further disclosed that eligible beneficiaries will receive continued support through, replacement of lost assets, financial literacy and business training, guidance on income generation and sustainability.
Monitoring teams are expected to conduct follow-up visits every six months to assess progress and ensure proper utilization of compensation funds.
CitiPower strongly advised the public to maintain a minimum distance of 25 meters on both sides of the transmission line.
The corridor is classified as a high-risk zone, and any encroachment could lead to fatal consequences.
The company also stressed that no compensation will be paid for any new developments erected within the transmission right-of-way after the compensation exercise.
The project aligns with Nigeria’s electricity transmission regulations and is part of broader efforts to improve power infrastructure and delivery across the region.